China starts construction of a second 200 MT/year reprocessing plant

| Mar. 21, 2021

Commercial bidding and purchase documents and other accounts suggest China is likely to start construction of a second spent fuel reprocessing plant of the same capacity and at the same site as its first such plant, the CNNC Gansu Nuclear Technology Industrial Park in Jinta, Gansu province.

Since 2015, China has been constructing a civilian "demonstration" reprocessing plant for spent light-water reactor fuel, with a capacity of 200 tons per year (tons of Heavy Metal, tHM/year). The construction activities and equipment purchases suggest that this first plant (Project I) could complete its civil engineering stage and begin equipment installment in late 2020. Project 1 is expected to be operational in 2025. The start of work on the second reprocessing plant (Project II) in late 2020 or early 2021 suggests that it could be commissioned before 2030.

In contrast to the launch of construction of Project I, there have been no official statements or news coverage so far concerning this new facility. There have been a number of announcements, however, including bid requests for various studies and services for "spent fuel demonstration reprocessing plant project II":

  • Jiangsu Shentong company, an equipment supplier, stated in a report dated 18 November 2019 that the China National Nuclear Corporation planned to build two 200 tHM/year reprocessing plants according to CNNC's 2012 "Long Teng 2020" (Dragon Soars 2020) technology innovation plan.
  • Bid for investigation of the impact of Project II on the environment and the adjacent community to be completed by 28 February 2021(posted on 5 November 2020).
  • Bid for supplementary investigation of average and extreme weather conditions in the Project II area for completion by 28 February 2021 (posted on 5 November 2020).
  • Bid for analysis of the environmental noise around the site of Project II, with completion required before 30 December 2020 (posted on 2 November 2020).
  • Bid for statistical analysis of meteorological parameters required for the design of the heating, ventilation, and air-conditioning system for Project II (posted on 9 December 2020).
  • Bid for design of auxiliary facilities for Project II with a bidding period of 28 February 2021 to 5 March 2021 (posted on 28 February 2021).
For more information on this publication: Belfer Communications Office
For Academic Citation: Zhang, Hui.“China starts construction of a second 200 MT/year reprocessing plant.” International Panel on Fissile Materials, March 21, 2021.